Construction Site Prep Cost Calculator
Site prep ranges $1.50–8.00 per sq ft depending on terrain, demolition, and utilities.
Total site prep
$31,320
Blended $/sf
$3
Contingency
$5,220
How the math works
Base = lot × (clearing + grading) + erosion + demo. Total = base × (1 + contingency).
12,000 × ($0.85 + $0.95) = $21.6k + $4.5k = $26.1k × 1.20 = $31.3k site prep.
How to Use
- Enter lot sq ft.
- Enter clearing $/sf.
- Enter grading $/sf.
- Enter erosion control.
- Enter demolition cost.
- Enter contingency %.
- Read total site prep.
Frequently Asked Questions
Site prep components?
Clearing/grubbing: $0.20–1.50/sf. Rough grading: $0.40–1.20/sf. Fine grading: $0.30–0.80/sf. Demolition (existing structure): $4–16/sf of structure. Erosion control (silt fence, BMP): $0.30–0.80/sf. Tree removal: $300–2,500 per tree. Stump removal: $200–800 per stump. Hazardous waste, contaminated soil: $30–200/cy. Dewatering pumps: $200–800/day. Add 15–25% contingency on greenfield, 25–40% on infill brownfield.
How does this impact project budget?
Construction budgets layer hard costs (50–65%), soft costs (15–25%), financing (5–10%), contingency (5–10%), and developer fee (3–5%). Schedule risk often equals or exceeds cost risk — every month delay carries carry cost (interest, real estate tax, insurance, opportunity cost) of 0.5–1.5% of project budget. This calculator quantifies one cost component.
Owner-controlled vs GMP vs CM-at-risk?
Lump sum/GMP: contractor takes risk above guaranteed maximum price, owner pays for change orders. CM-at-risk: open book, fee + GMP, more transparent. Construction management: agent for owner, GC subcontracted directly. Design-build: single accountability, faster but less price competition. Match delivery method to project complexity and owner sophistication.
Schedule and cost contingency?
Standard contingency: 10% of hard cost for entitlement, 5–8% for construction. Schedule contingency: 60–90 days buffer past target completion. Force majeure provisions: weather, material lead time, labor strike, permit delay. Track via critical path method (CPM) schedule. Major lender draws contingent on schedule + cost variance to budget remaining within 5%.
Related Calculators
More Finance Calculators
Browse all finance →AI Cost Calculator
Compare token costs across OpenAI, Anthropic, and Google AI models. Calculate monthly API spending for GPT-4o, Claude, Gemini, and more.
Tip Calculator
Calculate the perfect tip and split the bill between friends. Choose preset percentages or enter a custom tip amount.
Bill Splitter Calculator
Split an uneven restaurant bill by item, divide tax and tip proportionally, and see exactly who owes whom.
Discount Calculator
Calculate sale price, discount amount, stacked discounts, sales tax, and total savings for any markdown.
Gas Mileage Calculator
Calculate MPG or km/L, estimate trip fuel cost, and compare annual fuel expenses between two vehicles.
Sales Tax Calculator
Add sales tax to a price, reverse-calculate the pre-tax amount from a total, and estimate tax for multiple items on one receipt.
Keep exploring